
02/28/2018
New Headquarters Progress Update










3/31/2015
Moving begins















9/12/2014
Updates from the summer


1/17/2014
Framing for the offices is almost complete.



1/7/2014
Framing, Sheetrock, and electrical on the Shop Floor is almost complete.



11/5/2013
The concrete slab for the shop floor is nearing completion.



10/28/2013
Exterior painting nears completion. Sidewalks around the building are also starting to be poured.

9/23/2013
The mezanine steel for the offices has been completed.

8/20/2013
Painting has begun.

5/25/2013
Aerial photo taken the day that the ceiling deck was completed.


5/21/2013
Steel is complete and ceiling panels cover the majority of the building.


5/13/2013
The steel and roof almost complete.



5/2/2013
Steel continued.

4/29/2013
First steel column goes up.




4/24/2013
The wall panels are complete.




4/19/2013
The outer walls near completion.

4/12/2013
The first wall goes up.

3/28/2013
Aerial View of the finished foundation.